Command Center
Pasadena Refinery — Spring 2026 Turnaround — Day 6 of 21
Live · Day Shift
Thu 2 Apr 2026 · 14:22
↑ On pace
267 / 590
Welds Complete
Day 6 of 21 · 52 in progress
↓ −3.2 pts
91.8%
First-Pass Rate
Target: 95% · 3.2 pts below
↑ from $1.8M
$2.4M
Financial Exposure
2.1d schedule slip × $1.15M/day
+18 min
3.5 hrs
Avg Cycle Time
Weld start → VT complete
Daily Completion vs Target
Target: 50 welds/day to hold schedule
Scope Breakdown
590 total welds · 4 units
Passed267
In Progress52
Pending231
Rework28
Failed12
Contractor Performance
Turner Industries94.2%
Zachry Group5 drifts ⚠91.8%
Performance Contractors96.9%
Brown & Root Industrial7 drifts ⚠85.7%
Active Alerts
Welder cert expired — W-0345
5 min ago
Root gap exceeded — W-0212
18 min ago
Interpass temp exceeded — W-0188
1.2 hrs ago
Procedure Drift Alerts
Real-time violations flagged by FieldFlow across all contractors and units
Contractor Performance
Comparative view — all 4 active contractors this turnaround
First-Pass Rate Comparison
Target: 95% — dashed line
Turner Industries
Zachry Group
Performance Contr.
Brown & Root Ind.
Turner Industries
On Target
94.2%
24
Welders
187
Welds
11
Rework
2
Drifts
Zachry Group
Below Target
91.8%
18
Welders
142
Welds
15
Rework
5
Drifts
Performance Contractors
On Target
96.9%
21
Welders
163
Welds
5
Rework
1
Drifts
Brown & Root Industrial
Needs Intervention
85.7%
15
Welders
98
Welds
14
Rework
7
Drifts
Weld Map
CDU-3 · FCC-2 · HDS-1 · VDU-1 — click any joint for welder & status details